Henderson shipyard is set to become Australia’s most contested construction site—not just for submarines and frigates, but for tradies, suppliers, and delivery models that can stand up to global scrutiny.

The WA Defence Summit in Perth on 22 August 2025 featured one of the most anticipated conversations of the program: Constructing Australia’s Maritime Defence Future. The panel brought together senior leaders from contracting firms Built, DT Infrastructure, CPB and Georgiou to examine the challenges and opportunities of building the next generation of naval infrastructure in Western Australia.
The stakes are clear. Henderson shipyard and HMAS Stirling are set to undergo billions of dollars of investment to enable AUKUS submarine rotations, SEA 3000 Hunter-class frigate production, and sustainment facilities that must be ready by the late 2020s. This discussion unpacked the delivery task, the workforce challenge, the impact of AI and the vital role of local industry.

The Scale of the Infrastructure Task
Stephen Land, Chief Investment Officer at the Northern Australia Infrastructure Facility (NAIF), set the tone.
“We are not talking about incremental upgrades. These are generational assets—nuclear-capable facilities, submarine berths, frigate assembly halls, and the supporting logistics backbone. They will define WA’s role in Defence for decades.”
The panel agreed that Defence’s infrastructure requirements in WA amount to nothing less than a precinct-scale transformation. Henderson is evolving from a shipbuilding strip into a Commonwealth-owned strategic hub, integrated with partner facilities and aligned to AUKUS timelines. HMAS Stirling, meanwhile, must absorb new operational demands while maintaining its role as Fleet Base West.
Brendan Sowry, General Manager – Defence at CPB Contractors, highlighted the delivery pressure:
“The timelines are aggressive. By 2027, facilities need to be operational to host partner submarine rotations. That means detailed design, environmental approvals, procurement, and delivery models must be locked in now.”
For consultants and contractors, this compresses planning cycles and creates opportunities for those who can provide certainty on cost, risk, and schedule.
The Workforce Challenge
Perhaps the most repeated theme was labour. Estimates suggest as many as 10,000 skilled workers will be needed across civil, structural, marine, and specialist disciplines.
Mike Rinaudo, Head of Defence at DT Infrastructure, was blunt:
“Every contractor here knows the numbers don’t add up. The resources sector is pulling hard on the same pool of electricians, fitters, welders, and engineers. Defence infrastructure is competing head-to-head with iron ore expansions and energy transition projects.”
The panel acknowledged that Defence will need to develop strategies beyond wage competition. This includes accelerated training pathways, targeted migration, and partnerships with TAFEs.
Matthew Theoharous, Executive General Manager – Defence and Social Infrastructure at Built, pointed to sequencing as a risk management tool:
“We can’t mobilise 10,000 people overnight. But by staging packages logically—dry dock first, support buildings next—we can flatten the demand curve. Innovation in program sequencing will be just as important as innovation on site.”
For consultants, this highlights the need to embed workforce planning into early project definition. Advising Defence on realistic workforce mobilisation plans will be critical to shaping tenders that contractors can actually deliver.
Delivering Nuclear-Capable Facilities
Another recurring point was the complexity of nuclear-related infrastructure. While Australia is not building nuclear reactors, facilities must be designed to host and maintain nuclear-powered submarines.
Alex Gilliland, National Defence Manager at Georgiou, explained:
“The technical requirements are orders of magnitude above a normal wharf or maintenance shed. We’re talking international nuclear safety standards, restricted access protocols, and inspection regimes that require a new level of engineering assurance.”
This creates opportunities for specialist consultants in structural engineering, radiation safety, cyber-secure systems, and contamination controls. It also means Tier 1 contractors will be leaning heavily on trusted design partners and supply chains with Defence clearances.
Innovative Delivery Models
The panel also discussed how projects can be delivered within the time and budget envelope.
Sowry from CPB Contractors argued for new collaborative models:
“Traditional hard-dollar lump sum contracts won’t cut it for Henderson. The risk profile is simply too high. What we need are delivery models that bring Defence, designers, and contractors to the table from day one—alliancing, early contractor involvement, and open-book transparency.”
This was echoed by Rinaudo from DT Infrastructure:
“Innovation in delivery is not just about technology. It’s about governance and trust. If we keep adversarial contracting structures, we will lose time fighting over risk. If we embrace shared responsibility, we stand a chance of meeting the deadlines.”
For Defence estate consultants, this signals a shift. Advisory work will increasingly focus on shaping procurement models that balance accountability with collaboration. Understanding Defence’s evolving appetite for risk allocation is now a competitive edge.
Local Supply Chain Integration
A recurring theme was how Western Australian businesses can access the billions flowing into Henderson and HMAS Stirling.
Land from NAIF reminded the audience that:
“Local participation isn’t optional. It’s a mandate. But it has to be done within the framework of security and quality that Defence requires.”
The panel discussed supplier development programs and capability uplift initiatives as key pathways. Gilliland of Georgiou stressed the importance of structured engagement:
“Tier 1 contractors can’t just tick a box on local content. We need genuine partnerships—helping SMEs understand security clearances, documentation standards, and QA requirements. That’s the only way local firms can scale into this environment.”
This presents opportunities for consultants to act as bridges—helping WA firms prepare for Defence work, guiding them through compliance, and linking them to major contractors.
What the Panel Said on AI
When asked about the role of artificial intelligence in delivering WA’s Defence infrastructure program, the panellists struck a cautious but optimistic note.
Stephen Land observed: “AI can help us see risks earlier and make better decisions, but it won’t pour the concrete.” Others agreed, pointing to applications in project scheduling, design coordination, and workforce planning. Yet the consensus was clear: AI may streamline processes, but it won’t solve the fundamental pressures of labour shortages, material supply, or nuclear-capable assurance standards.
The takeaway? AI will be an enabler, not a silver bullet—and any deployment will need to meet Defence’s stringent security requirements.
Implications for Defence Estate Planning
While the panel’s focus was on Henderson and Stirling, the implications extend across Defence estate planning.
First, the need for workforce staging and supply chain integration will affect project scheduling nationally. Projects at Fleet Base East or Darwin will be competing with WA for skilled labour. Second, the push for collaborative contracting models may spill over into the broader Estate Works Program, where Defence could look to replicate lessons learned.
Most importantly, the technical requirements of nuclear-capable facilities will set a new benchmark for infrastructure assurance across the estate. Consultants should expect heightened scrutiny on safety, security, and compliance even in non-nuclear projects.
Opportunities for Consultants and Contractors
For those working in the Defence estate sector, the panel’s insights boil down to three opportunity streams:
- Strategic Advisory – Supporting Defence to shape procurement models, sequencing, and workforce mobilisation plans that are realistic and defensible.
- Specialist Design and Assurance – Providing niche expertise in nuclear safety, cyber security, structural resilience, and environmental compliance.
- Local Industry Enablement – Guiding WA SMEs through Defence accreditation, supply chain integration, and capability uplift.
These align closely with Defence’s stated objectives of timely delivery, sovereign capability, and industry participation.
Conclusion
The Henderson and Stirling build programs represent the most ambitious Defence infrastructure effort in Western Australia’s history. They are also a test case for how Australia manages the intersection of sovereign capability, international collaboration, and industrial competition.
The panel was clear: success will require collaboration, innovation, and a relentless focus on delivery.
As Sowry concluded:
“We’re not just building sheds and wharves. We’re building the backbone of Australia’s maritime defence. If we get it right, WA will be at the centre of regional security for the next fifty years.”
For consultants and contractors, the message is equally clear. Now is the time to position capability, invest in partnerships, and prepare to deliver under some of the most challenging but rewarding conditions the industry has ever faced.