Defence’s Estate Works Program announced for 2027

Business news Contractor Opportunity Estate Works Sustainment

By Darian Macey, October 27 2026

Defence’s new Estate Works Program (EWP) forecast is slightly larger than February’s, but the headline count conceals a substantial reset.

Of the 211 projects now listed, 104 are new to the forecast. Another 107 carry over from February, almost all with later tender windows. Meanwhile, 91 February entries have disappeared from the list.

For contractors and suppliers, the list is useful for selecting markets and building relationships – albeit a risky basis for forecasting near-term revenue.

Figure 1. February 198 less 91 absent entries plus 104 new entries equals October 211. New means new to this forecast comparison, not necessarily a new project or funding approval.

The new forecast was released on 26 October and is correct as at 24 September. It covers October 2026 to September 2027; February’s covered the remainder of 2026.

The analysis below follows the February cohort through the tender and contract records available to DECNET, then examines the mix of the new list. It concerns the EWP as distinct from Defence’s capital works program.

What happened to the February projects

Fifteen of February’s 198 project codes have already been awarded. A further Cultana subpackage award shares a project reference, but the precise relationship to the full forecast scope remains unconfirmed.

Figure 2. Status reconciliation at 27 October 2026. Closed or recorded evaluation includes 39 readable closed tenders and four Helyx evaluation records. Open or recorded procurement includes 12 live tenders and two records whose final close could not be verified. [3, 4]

Another 43 projects have closed RFTs but are yet to be awarded. 14 are currently open for tender. 98 remain forecast; the remaining 27 are absent from October without a tender or award identified.

The 27 unresolved cases are a visibility gap, not evidence of cancellation. They may have been deferred, re-scoped, bundled into other packages or progressed through limited tender.

The 15 matched awards represent 7.6 per cent of the February cohort.

Later tender dates dominate the carry over

Of the 107 codes common to both forecasts, 106 now have a later tender quarter. The median movement is two quarters. Forty-seven move back by two quarters, 27 by three quarters and 14 by at least a year. Only Fleet Base West Infrastructure Upgrade S-EST11243 retains its original quarter.

Figure 3. Change in published tender quarter for the 107 common project codes. A quarter movement is not a measured delay to contract award or construction completion. [1, 2]

Some movements are substantial. Fairbairn S-EST10531 moves from Q1 2026 to Q1 2027. Learmonth sewerage and infrastructure S-EST11085 moves from Q3 2026 to Q2 2027. Four packages, including Tindal HVAC S-EST09931, move from Q2 2026 to Q3 2027.

Figure 4. October forecast by calendar quarter, separating retained codes from new entries. These are intended tender releases, not construction starts or expenditure. [1]

October to December contains 77 packages, but 65 are carry-over projects. By contrast, 92 of the 104 new entries are dated in 2027. Overall, 134 of 211 packages sit in 2027. The near-term list is dominated by older work; most of the genuinely fresh forecast entries sit further out.

The regional mix is changing

Figure 5. Published PDS regions, preserved for a like-for-like comparison. These are not exact physical state boundaries: the ACT allocation includes HMAS Creswell in Jervis Bay Territory and, in October, Eden Wharf in NSW. [1, 2]

The Northern Territory is the clearest expansion in the opportunity list, increasing from 25 to 43 packages, or 72 per cent. It combines 20 carry-over projects with 23 new entries. That is both a larger pursuit pool and a sizeable stock of work that has remained in the forecast.

Queensland rises from 32 to 36, but 28 of October’s entries are new and only eight carry over. Its modest net increase therefore conceals much more turnover than the NT. NSW looks stable at 55 versus 54 packages, yet 38 are retained and 16 are new.

WA rises from 23 to 27. SA falls from 24 to 15 and Victoria from 25 to 19. Those reductions should not be read as equivalent falls in expenditure or strategic importance: awards and completed tenders leave the forecast. NT, Queensland and WA together account for 106 entries, just over half the new forecast, compared with 80 of 198 in February.

Established bases still need practical trades

Figure 6. DECNET classification from named sites and project titles. Each package is counted once; joint, broad and multiple-site packages retain separate categories. It is an analytical classification, not a Defence coding field.

Air bases and air ranges account for 81 October packages, up from 66 in February. Army bases and land training sites account for 60, up from 57. Together they represent 141 of 211 entries, or 67 per cent. Naval and maritime sites account for 30. This is predominantly work on the existing estate, often requiring access and staging around continuing operations.

What hides beneath the project title

Figure 7. Keyword classification of October works descriptions.

October provides a detailed trade column that the February forecast did not contain. Electrical and power work appears in 132 packages, structural work in 113, mechanical or HVAC in 80, and hydraulic, water or sewer work in 63. These counts describe participation opportunities within packages, not separate contracts or shares of spend. Specialist suppliers may have a wider addressable market than headline project titles suggest.

Larger packages reflect a different mix

Figure 8. Project counts by official indicative budget band. Values are not summed: the highest band has no stated ceiling. [1, 2]

The $8 million-plus band increases from 16 projects to 29, lifting its share from 8.1 to 13.7 per cent. Twenty-one of October’s 29 large-band projects are new entries. The market has more large packages to assess, but this is not evidence that every existing job has become more expensive.

Among the 107 retained projects, 80 keep the same band, 18 move down and nine move up. Scope changes, packaging and inflation may all contribute; the forecast does not explain the causes.

Figure 9. Provider names normalised across editions: February BVBI is Bureau Veritas; Mott Mac is Mott MacDonald. Counts measure forecast allocations, not contract wins, provider capacity or delivery performance.

The PDS allocation also changes. Aurecon’s count falls from 99 to 72, Bureau Veritas rises from 50 to 77 and Mott MacDonald from 49 to 62. Aurecon’s share moves from half the list to roughly a third.

A closed tender can mean months of waiting

Across 29 matched EWP works contracts whose original award notices were published from June to 27 October 2026, the median interval from final tender close to recorded contract commencement is 123 calendar days. The median from tender close to public award notice is 138 days. Twenty-one cases exceed 90 days to commencement; seven exceed 180 days.

Figure 10. Time period from tender close to contract commencement. [4]
Project and contractFinal closeContract startDays
Gallipoli refurbishment  CN42593437 May 202629 Jun 202653
Williamtown refurbishment  CN428241324 Jul 202612 Oct 202680
Amberley refurbishment  CN428241622 Apr 202628 Sep 2026159
Tamworth GRES  CN428241913 Oct 20251 Oct 2026353
Selected cases. The final close is taken from the AusTender ATM notice, including extensions. Contract dates come from the original CN record.

The range is 53 to 353 days. In the seven October-published cases the median is 159 days, compared with 123 days in 19 July-to-September cases. That later sample includes long-running older tenders, so it does not establish a general deterioration in evaluation performance.

For bidders, the commercial implication is straightforward: model several months between closing a bid and receiving a contract, test a longer case, and monitor tender validity, resource availability and pricing assumptions. A forecast quarter, a tender deadline and a contract commencement date can be vastly different.

Regional winners are more useful than a national league table

DECNET identified 80 project-linked EWP or related Service Delivery Division works award notices published between 28 October 2025 and 27 October 2026. Seventy-four could be allocated to a physical region. The ranking below uses their original awarded values, including GST, and counts each CN once. It excludes PDS fees, base services, utilities and major Infrastructure Division contracts.

Figure 11. Regional leaders by value

Jordi Construct leads NSW by value on a single $36.6 million Richmond contract, while Duratec has three recorded NSW awards worth $13.4 million. In WA, PCB Contractors has eight located awards worth $18.6 million. APGC has five Queensland awards worth $17.1 million and three Victorian awards worth $10.2 million. BILD’s three SA awards total $21.8 million. Larrakon leads NT, with four awards worth $12.49 million.

For a subcontractor, repeat wins can be more useful than the largest single contract. They indicate an observed flow of relevant packages to a contractor.

What suppliers should do with the forecast

The forecast supports a targeted pursuit plan. The strongest current opportunity signals are a larger NT list, substantial fresh Queensland work, a heavier large-project band and widespread demand for electrical, structural and building-services capability.

Select packages by capability and place

Match the actual work types, operational constraints and location to your delivery footprint. A broad refurbishment title can conceal electrical, mechanical, hydraulic and structural work. Address Indigenous procurement eligibility early, not after the RFT lands.

Refresh relationships and timing

Check the current PDS provider for each code, establish the likely procurement route and commence direct engagement early.

Separate pipeline stages in the sales forecast

Keep track of projects as they progress through the various stages, eg. forecast, advertised, closed, awarded and mobilising work. Allow for a three-to-six-month decision interval in pursuit planning.

The new forecast offers a worthwhile pool of work. The advantage will sit with suppliers who can identify the right packages early and stay close to their actual progression, without committing capacity on the strength of an indicative quarter alone.

Track Defence estate opportunities, tender changes and contract awards with Helyx.

Analysis cut-off 27 October 2026. Forecast data correct as at 24 September 2026. All counts refer to project packages or contract notices as specified; they are not measures of expenditure.

Definitions

MeasureDefinition
New forecast entryOctober project code absent from the original February PDF. 104 entries; distinct from the 102 new Helyx records created during import.
Carry over and absentExact numeric project identifier matched across PDFs, allowing S-EST versus EST and hyphen typography. 107 common codes and 91 February codes absent in October.
Award matched15 February codes with a matched whole-package CN in the reviewed records. Cultana S-EST10731-1 is kept separately because its full-scope attribution is inferred.
Closed or evaluation39 readable closed construction RFTs and four recorded evaluation cases, without a matched award identified. This does not establish that evaluation is still active.
Open or recorded procurement12 construction tenders closing after the cut-off plus two procurement records whose final close was not verified.
Still forecast and delayed98 common-code packages remain at forecast stage; 97 have later quarters than February and one is unchanged. All 107 common codes show 106 later quarters.
Missing and unresolved27 February codes absent from October without a tender or award identified in the reviewed records. No cancellation is inferred.
Time to award proxiesFinal published construction tender close to recorded contract start, and separately to original public award notice. 29 matched cases with notices from June to 27 October 2026.
Regional contractor sample78 project-linked Service Delivery works CNs published over the preceding 12 months. 72 located and six unallocated. Original values, one count per CN; no amendment double-counting.

Regional contractor detail

Physical regionContractorOriginal awardsCN count
NSWJordi Construct$36.62m1
 Duratec$13.39m3
 Baseline Projects$3.68m1
ACTDuratec$11.59m1
 Shape$7.40m1
 Form Projects$5.68m1
NTAKJ Services$9.89m1
 Larrakon$7.05m2
 Wurrba$3.21m1
QLDAPGC Group$17.14m5
 Apollo Property Group$15.23m3
 Shamrock Civil Engineering$5.10m3
SABILD Infrastructure$21.82m3
 McMahon Services$10.49m2
 Wamarra$4.08m1
VICAPGC Group$10.20m3
 Baseline Projects$7.15m1
 Eastern Property Services$4.71m2
WAPCB Contractors$18.56m8
 Duratec$5.03m1
 Waalitj-Hydroflow$1.96m1
JBTForm Projects$1.49m1
Top three by original awarded value in each located region. No qualifying located Tasmanian award was established in this sample; this is not evidence of no Tasmanian activity. Six unallocated notices are excluded from the region tables.

Sources

[1] Department of Defence. Estate Works Program Update, Tender Forecast October 2026 to September 2027. Released 26 October 2026; correct as at 24 September 2026. Nine-page source PDF; 211 project entries.

[2] Department of Defence. Estate Works Program Update, Tender Forecast February to December 2026. Released February 2026; correct as at 18 February 2026. Original ten-page source PDF retained by DECNET; 198 project entries. Later May refreshes have not been substituted for the original baseline.

[3] Helyx project, contract and event exports,

[4] Department of Finance, AusTender.

Darian Macey
Author: Darian Macey

Darian is a former Engineering Officer with the RAE with tertiary qualifications in Engineering and Project Management. He is a leading practitioner within Australia's NSI sector with previous employment in Government, project management and building contractor organisations.

chatsimple