By Darian Macey, April 2 2025
Being on the Defence Infrastructure Panel – Major Contractors (DIP-MC) is just the first step – securing work still requires going through an engagement (tender) process for each project.

The DIP-MC engagement process closely mirrors a standard tender, with a few panel-specific twists to be aware of:
Key things to remember in DIP-MC engagements:
- Only invited panellists can bid (no outside bidders, unless Defence breaks from the panel).
- You must have the appropriate state building licence, or you won’t be invited.
- You must sign the DCA before getting tender docs.
- Use the panel tender templates, not the old ones (they won’t even be provided to you).
- Tenders will be evaluated with the same rigour as any Defence tender – competition remains tough.
- Being on the panel is a privilege, but you still need to win each project on merit!
Flexible Delivery Models (and Their Risk Profiles)
One of the strengths of DIP-MC is its flexibility in delivery models. Defence isn’t limited to a one-size-fits-all contract – they can choose the best delivery method for each project, and the panel contractors must be prepared to work under various models. The Panel Agreement allows engagements under five delivery models, each with different risk allocations and collaboration levels. Here’s an overview of each model and what it means for contractors:
In summary, DIP-MC allows Defence to pick the right tool for the job. Whether it’s a straightforward build (Construct Only), a turnkey package (D&C), a collaborative journey (ECI/Managing Contractor), or something in between, the panel has it covered. As a contractor, be ready to operate under any of these models. Each comes with different roles and risks, so ensure your team is versed in all five and tailor your bid strategy accordingly. The good news is that all panel members have been pre-qualified on the basis of demonstrating capability across these delivery methods.
How DIP-MC Procurement Differs from Standard Defence Contracts
If you’re familiar with the traditional Defence Suite of Facilities Contracts (the “Suite”) and the usual open tender process, you’ll find much of DIP-MC business-as-usual – but there are some key differences and efficiencies baked into the panel system. Here are the major ways DIP-MC procurement departs from the standard procedures:
Dedicated Panel Templates & Conditions:
DIP-MC tenders use panel-specific templates that reference the Panel Deed and obligations unique to panellists. These templates replace the typical ASDEFCON documents and exclude steps like the usual “Invitation to Register Interest,” making for a one-stage procurement. For contractors, this reduces duplication but requires close attention to the panel’s modified formats.
Exemption from the GPJR Act:
DIP-MC procurements are not considered “covered procurements” under the Government Procurement (Judicial Review) Act 2018. That means panellists cannot seek legal redress under the Act for tender disputes. This reduces the likelihood of delays and highlights the importance of resolving issues during panel establishment. Defence’s internal complaint pathways still apply.
Streamlined Compliance and Documentation:
Since panel contractors were already vetted at the time of appointment, many standard schedules are omitted in subsequent tenders. This includes documents like WHS accreditation, financials, or prior performance history. However, contractors must maintain these credentials throughout the panel term and notify Defence of any changes. The reduced admin allows panellists to focus on project-specific solutions.
Alignment with Policy Requirements:
DIP-MC tenders are structured to comply with major Commonwealth policies by default. These include the Indigenous Procurement Policy, the Defence Policy for Local Industry Participation, the Environmentally Sustainable Procurement Policy, and the Australian Skills Guarantee. All projects over $200M qualify as “Flagship Construction Projects,” which means higher workforce targets and skills commitments. Panel templates incorporate these requirements from the outset.
Panel-Specific Contract Conditions:
Contracts awarded under DIP-MC will reference the panel deed, with several overarching obligations managed at the panel level—such as security, insurance, and performance. Joint bids are allowed (if both parties are on the panel and invited), which wasn’t typical in the old system. While project contracts are slimmer, all panel obligations still apply.
In Summary:
DIP-MC delivers efficiency by reducing procurement lead times and paperwork. For panellists, this means leaner tenders and faster processes—but also a need to remain alert to ongoing compliance. For subs and consultants, less documentation may be requested, but expectations around local content, Indigenous engagement, and skills development remain high.
Tips for Panel Contractors: Staying Compliant and Competitive
Getting on the DIP-MC panel was no small feat – now the focus shifts to staying there and winning work. Here are six practical ways to keep your edge:
1. Know Your Obligations
Panel membership comes with ongoing requirements. These include maintaining insurances, WHS accreditation, and compliance with workplace laws (e.g. gender equality). You must notify Defence of any major changes such as restructuring or compliance lapses. Treat the panel deed as a live contract – failure to meet these obligations can lead to suspension.
2. Attend Mandatory Training
Defence expects your Panel Manager (and possibly others) to attend training sessions – either in person or via webinar. These sessions help ensure you’re using panel processes correctly and understanding evolving expectations. Project-specific training may also be required, such as systems briefings or compliance refreshers. Internally, ensure your broader team (estimators, PMs, legal) is across DIP-MC requirements.
3. Maintain Licences and Security Clearances
To be eligible for projects, you must hold the relevant construction licences in the project’s jurisdiction. If you’re planning to expand your footprint, secure licences early. Also, consider your DISP membership. While not mandatory for all projects, classified works may require it. Start security clearances for key staff well in advance to avoid delays.
4. Respond Promptly to EOIs
If Defence sends an Expression of Interest (EOI), reply clearly – even if declining. This helps position your business for future work. If you’re interested, show it. Share your capacity, interest and early ideas. And if things change (new capabilities, resourcing limits), update the Panel Manager. Communication helps influence who gets invited next time.
5. Stay Sharp on Tenders
Even as a panellist, competition is tough. Your tender submissions must strictly conform to instructions. Defence will judge on value, not just price. Emphasise your technical approach, delivery method, and team. Highlight prior experience and lessons learned from panel engagements. Be especially clear in meeting policy objectives around Indigenous participation, local content and skills development.
6. Monitor Changes and Performance
Keep up with any updates to panel documentation, policy targets or templates. SEG may issue new requirements. Track your own performance – Defence will. Consistent delivery, responsiveness and collaboration build trust and increase your chance of future awards. Review any panel feedback mechanisms and keep refining your offer.
Ready to Succeed with DIP-MC?
DIP-MC is more than just a streamlined panel arrangement – it represents a significant shift in how major Defence infrastructure projects are procured and delivered. While the panel offers efficiencies and clarity, it also demands professionalism, preparedness, and performance from its members. Contractors must stay agile, keep up with compliance and policy shifts, and continue proving their value on every project. With flexible delivery models, standardised templates, and a clear emphasis on broader government priorities, the panel creates a consistent but competitive playing field. Success lies not just in being on the panel, but in understanding the nuances of how it operates – and executing each engagement with precision and purpose.
➡️ Download the DIP-MC contact list to get in touch with the 18 panel firms. Start conversations and build partnerships – early engagement can position you for success.
➡️ Subscribe to the DECNet Defence Estate newsletter for ongoing updates, insights, and tips about Defence infrastructure projects. The landscape will evolve, and staying informed is the best way to stay ahead of the curve.
➡️ Subscribe to the DECNet Defence Estate newsletter for ongoing updates, insights, and tips about Defence infrastructure projects. The landscape will evolve, and staying informed is the best way to stay ahead of the curve.
➡️ Take our online course Mastering Defence Infrastructure to learn everything you need to know to grow your business or grow your career in this exciting sector.
➡️ Share this guide with your colleagues, bid teams, and industry partners. Preparation is a team effort – make sure everyone involved in your Defence projects understands the panel’s ins and outs, from your project managers to your legal advisors and subcontractors.
By being proactive, compliant, and collaborative, you can make the most of the DIP-MC era. Defence’s infrastructure needs are vast and challenging – but with the right approach, the new panel will unlock efficient delivery and robust opportunities for those ready to rise to the occasion. Good luck, and see you on site!